What are the charger/installation site types?
Charger/installation site types refer to the following:
New: No electrical infrastructure is in place. Conduit installation is acceptable.
Stub-out: Includes at least 2-inch minimum spare conduit run with pull rope that is sized, installed and located per the National Electrical Code for future installation of wiring supporting up to a 480-volt AC, 4-wire, 125-kilowatt (kW) load.
Replacement/Make-ready: Existing site wired with all the electrical infrastructure needed to support the installation of EV charging. Replacements are allowed only for units capable of delivering 40 kW or less.
Project