What supporting documents do I need to submit for my application approval?
Required supporting documentation depends on your relationship to the project site:
For Site Owners
- Signed copy of your Application form
- Complete copy of the purchase invoice for equipment
- Complete copy of design and engineering invoice
- Complete copy of the purchase invoice for all installation costs
- Copy of your permit
- Copy of your final inspection card
- If applicable to your installation, a utility service order
- At least two photos showing all installed and operational equipment; one photo should clearly show CALeVIP labels appropriately affixed to the chargers
- Photo of each equipment serial number
- Copy of a network agreement for the chargers
- Minimum of five-year term of service for DC fast chargers
- Minimum of two-year term of service for Level 2 chargers
- Completed Installation Data form
- After equipment is operational, a Charging Session Data file
For Non-Site Owners
- Signed Site Verification form confirming that the applicant is allowed to install the equipment at the site
- Signed copy of your Application form
- Complete copy of the purchase invoice for equipment
- Complete copy of the design and engineering invoice
- Complete copy of the purchase invoice for all installation costs
- Copy of your permit
- Copy of your final inspection card
- If applicable to your installation, a utility service order
- At least two photos showing all installed and operational equipment; one photo should clearly show CALeVIP labels appropriately affixed to the chargers
- Photo of each equipment serial number
- Copy of a network agreement for the chargers
- Minimum of five-year term of service for DC fast chargers
- Minimum of two-year term of service for Level 2 chargers
- Completed Installation Data form
- After equipment is operational, a Charging Session Data file